LOCATION
Laramie, Wyoming
OWNER
City of Laramie
GENERAL CONTRACTOR
Mechanical Systems Inc.
ENGINEERS
AVI Engineers - Cheyenne, Wyoming
COMPLETION DATE
2017
CONTRACT AMOUNT
$5,545,155
SCOPE OF WORK
Lining 20” domestic water transmission line
PROJECT DESCRIPTION
Mechanical Systems, Inc. was the lead contractor for this design build construction project. One of the domestic water lines that feeds the City of Laramie is a 19-mile-long, 70-year old, 20” steel pipeline. MSI, along with AVI Engineers and United Pipeline, lined the existing water transmission line with a 20” HDPE liner. The length completed was 92,400 feet, from west of town to the east just short of the Laramie River. Construction of the project was started in February and completed in July.